The review and its timeline

Berg needs both a provincial environmental assessment and, very likely, a federal impact assessment. BC has asked Ottawa to let one provincial review stand in for both. This page sets out what has happened so far and the schedule the company proposes.

In brief

Surge Copper filed its Initial Project Description with the Environmental Assessment Office (EAO) and the Impact Assessment Agency of Canada (IAAC) on September 9, 2026. Two days later the EAO asked the federal government to substitute BC's process for the federal one. On September 15 the EAO approved the IPD and engagement plan by order, and Early Engagement began. The company's own schedule targets provincial and federal decisions in the third quarter of 2029 and a "construction-ready" status by the fourth quarter of 2030.

Sep 9, 2026IPD received by the EAO and IAACSource: EAO substitution request, Sep 11, 2026, p. 1; EAO substitution request, Sep 11, 2026, p. 2.
90 dayslegislated length of Early EngagementSource: IPD, p. 5-7, Table 5.6-1.
Q3 2029company target for the BC certificate and the federal decisionSource: IPD, p. 5-8, Table 5.6-1.
Q4 2030company target for all federal authorizations and construction readinessSource: IPD, p. 5-8, Table 5.6-1.

Why Berg is reviewable

The project receives no federal funding and uses no federal land. Source: IPD, p. 5-2.

The record so far

  1. Feb 2026Surge tells the Nations that Berg has been accepted into BC's Critical Minerals Office, "a designation intended to improve government coordination for priority critical mineral projects without changing regulatory or consultation requirements". Source: IPD, p. 6-11, Table 6.6-1.
  2. Sep 9, 2026The EAO's Chief Executive Assessment Officer receives the IPD; IAAC receives it the same day. Source: EAO substitution request, Sep 11, 2026, p. 1; EAO substitution request, Sep 11, 2026, p. 2.
  3. Sep 11, 2026The EAO writes to the President of IAAC requesting substitution. Source: EAO substitution request, Sep 11, 2026, p. 1.
  4. Sep 15, 2026Section 13(3)(a) order: the EAO's Acting Project Assessment Director approves the IPD and engagement plan. The same day the EAO and IAAC send a joint letter to Nations. Source: Section 13(3)(a) Order, Sep 15, 2026; Witset First Nation notice, Sep 29, 2026, p. 2; Anaskaski House notice, Oct 14, 2026, p. 1.
  5. Sep 29, 2026Witset First Nation asks to be a participating Nation. Source: Witset First Nation notice, Sep 29, 2026, p. 1.
  6. Oct 2, 2026Wet'suwet'en First Nation asks to be a participating nation. Source: Wet'suwet'en First Nation notice, Oct 2, 2026.
  7. Oct 14, 2026The House of Anaskaski gives notice as a Participating Indigenous Governing Body. Source: Anaskaski House notice, Oct 14, 2026, p. 1.
  8. Oct 15, 2026Skin Tyee First Nation asks to be a participating Indigenous nation. Source: Skin Tyee First Nation notice, Oct 15, 2026.

More on each notice is on the First Nations page.

The Section 13(3)(a) order

The IPD's stated purpose is to initiate the provincial and federal processes, and section 13(1)(b) of the Environmental Assessment Act requires the engagement plan that accompanies it. Source: IPD, p. 1-3; IPD, p. 1-4. The order of September 15, 2026 records that Surge's submission "satisfies the Environmental Assessment Office guidelines" and approves both documents. It describes the project as 120,000 tonnes of ore a day, "equivalent to approximately 43 million tonnes per year, over a 28-year operational mine life". It is signed by Chelsea Garside, Acting Project Assessment Director. Source: Section 13(3)(a) Order, Sep 15, 2026.

Substitution

Under the Impact Assessment Cooperation Agreement between Canada and BC, the federal Minister can let BC's assessment stand in for the federal one. The IPD calls this "one project, one assessment". BC's assessment would then also have to meet federal requirements, and the EAO would report to both governments' ministers. Source: IPD, p. 5-1; IPD, p. 5-2.

The EAO's letter of September 11, 2026, from Acting Chief Executive Assessment Officer Danielle Smyth to IAAC President Terence Hubbard, makes the request now so that IAAC can consult on it during a planned joint comment period. Its main points are these:

The letter also cites a March 2025 commitment statement between BC and Canada on coordinated permitting for critical mineral projects. Under it the EAO and IAAC are running a joint process for BC's Early Engagement and IAAC's Planning phase. Source: EAO substitution request, Sep 11, 2026, p. 2.

The company's schedule

Table 5.6-1 of the IPD is Surge's critical path to a construction decision. The legislated durations come from the statutes; the target dates are the company's.

StageLegislated durationCompany targetMilestone
Pre-EA preparationProponent drivenQ4 2025 to Q4 2026IPD and engagement plan submitted; baseline programs continue
Early Engagement90 daysQ4 2026 to Q1 2027Joint Summary of Issues and Engagement; EAO identifies Participating Indigenous Nations
Detailed Project DescriptionAbout 60 days (proponent driven)Q1 2027Detailed Project Description and draft Application Information Requirements; a substitution decision may come at this stage
Readiness decisionNone setQ1 2027EAO decides whether the assessment can begin
Process planning120 days minimumQ2 to Q3 2027Process Order, information requirements, assessment plan; Technical Advisory Committee formed
Application developmentAbout 12 to 18 months (proponent driven)Q1 2027 to Q2 2028Application for an Environmental Assessment Certificate submitted
Application review180 days maximum, plus about 45 daysQ2 2028 to Q1 2029Public comment period; revised application
Effects assessment and recommendation150 days maximumQ1 to Q3 2029Assessment Report and proposed conditions; IAAC draft Decision Statement
Provincial decision30 days maximumQ3 2029Environmental Assessment Certificate
Federal decision30 days maximumQ3 2029Decision Statement
BC permitsNone set2028 to 2029All BC approvals; the certificate must come first
Federal authorizationsNone setQ4 2030All federal authorizations; construction-ready status

Source: IPD, p. 5-7, Table 5.6-1; IPD, p. 5-8, Table 5.6-1. Some wording is shortened.

Surge intends to seek permits at the same time as the assessment "where supported by regulators", and expects clarity on that "over the coming months". Source: IPD, p. 5-2.

Our assessment. We assess the schedule as a proponent's best case. Early Engagement has a fixed 90 days, but most later stages run on the company's preparation time and the EAO's readiness decision. The Tenas coal review next door, documented at telkwa-coal.ca, shows how information requests can extend those stages by years.

Permits after the assessment

The IPD lists the permits it expects to need. By our count Table 5.4-1 lists 24 provincial permits and approvals and Table 5.4-2 lists 11 federal ones, and both tables are marked preliminary. Source: IPD, p. 5-3, Table 5.4-1; IPD, p. 5-6, Table 5.4-2. The largest are:

How to take part

The EAO's letter says a joint public comment period is to be held "shortly". The seven documents on the registry do not yet give its dates. Surge plans public open houses in Smithers and says public engagement begins in Early Engagement. Source: EAO substitution request, Sep 11, 2026, p. 2; IPD, p. 7-5; IPD, p. 7-10.

Sources

  1. Surge Copper, Initial Project Description and Engagement Plan, September 2026: chapters 1 and 5
  2. EAO to the Impact Assessment Agency of Canada, substitution request, Sep 11, 2026
  3. EAO, Order under Section 13(3)(a), Sep 15, 2026
  4. Notices of intent to participate: Witset, Wet'suwet'en First Nation, House of Anaskaski, Skin Tyee

Page references give the printed page label; each link opens the PDF at that page.